Thursday, July 24, 2014
Loading...





Goshen Board of Public Works and Safety and Stormwater, Sept. 16, 2013

Goshen Board of Public Works meeting of Sept. 16, 2013
Posted on Sepa. 18, 2013 at 1:00 a.m. | Updated on Sepp. 18, 2013 at 1:41 p.m.

Goshen Board of Public Works and Safety and Stormwater

When: Monday, Sept. 16

Key action: Promoted Pvt. Jerod Erb to the rank of sergeant in the Goshen Fire Department effective Thursday, Sept. 19.

Other actions:

Ÿ Accepted easements, right-of-way and the plat for the Growing Kids Learning Center subdivision at 3202 and 3212 Elkhart Road and 2909 Peddlers Village Road.

Ÿ Accepted three balancing change orders for the Maple City Greenway-Fidler Pond, Dickerson Landing phase two and the Electric Brew bump-out projects. The Maple City Greenway-Fidler Pond project required more topsoil removal than anticipated, which led to an increase of $14,857.06 for a final contract price of $77,884.56. The Dickerson Landing change order increased the price by $2,252.04 for a total contract price of $177,226.79. The Electric Brew bump-out required additional removal of concrete that was removed from the alleyway due to its poor condition that would not provide a good transition for the new concrete to tie into. The increase to the price was $4,095.89, bringing the total contract price to $13,296.48.

Ÿ Approved and accepted water main and sanitary sewer infrastructure at Keystone RV for maintenance.

Ÿ Declared 821 water meters as surplus property and resolved to see the meters as such.

Ÿ Announced the state’s bid for untreated road salt was bid out to Cargill at $61.43 per ton. The city’s requirement was for 1,300 tons and the 2012 price was $62.71 per ton.




Loading...
Loading...
Loading...
Back to top ^